Tacloban port REhabilitation phase 4
The Port Rehabilitation Project was completed in 16 months, 9 months ahead of schedule.
Phase 2 and 3 were also built by Marra Builders, Inc. Phase 2 was finished ahead of schedule, and Phase 3, a month ahead of schedule.
TACLOBAN PORT REHABILITATION PROJECT PHASE 1
The works include the demolition and excavation of the existing structure, pile driving of tubular sheet piles and concrete anchor piles, placement of steel tie rods, supply and placement of rocks on the sheet pile wall, correction dredging, supply and compaction of selected fill, a well as the supply and placement of interlocking paving blocks. A Roro ramp were also constructed for this project.