DESIGN AND CONSTRUCTION OF LPG JETTY FACILITY



In 2016, Marra Builders, Inc. was awarded the contract for the design and construction of an LPG receiving jetty in Sariaya, Quezon.



DESIGN AND CONSTRUCTION OF LPG JETTY FACILITY



The access trestle is 750 meters in length and the entire Jetty Facility, including the rock causeway, loading platform and steel catwalks were completed in 11 months.



DESIGN AND CONSTRUCTION OF LPG JETTY FACILITY



Items of work also includes the platform for fire/spill protection as well as the fabrication and installation of the galvanized pipe racks.



DESIGN AND CONSTRUCTION OF LPG JETTY FACILITY



Trelleborg 100T Mooring Bollards and SCN Rubber Dock Fenders were used for this project. Completed on time and on budget.