Extension of the RC Wharf and the Construction of a Backup Area



On December 6, 2018, Marra Builders was awarded the contract to work on the Extension of the RC Wharf and the Construction of a Backup Area in the Port of Cawit, Boac, Marinduque.



Extension of the RC Wharf and the Construction of a Backup Area



Work officially started on February 28, 2019 and was expected to be finished on April 22, 2020, in 420 calendar days. The scope of work involved the extension of the existing RC wharf, widening of RC platform, and the construction of a back-up area as well as widening of the existing access trestle.



Extension of the RC Wharf and the Construction of a Backup Area



Marra Builders was able to complete the project on November 25, 2019, 5 months earlier than the expected date of completion.